CBD Project Update

  • CBD Project Update

Work continues along Murray Street

Paving on Murray Street, part of the CBD revitalisation project, is expected to be done by November, with 39 percent completed so far.

Article continues below

Planning for median strip demolition work will commence this week for the entire length of the project from Corangamite street to Queen street.

Meanwhile, exposed aggregate will be laid in front of Culture and Hulms Bakery.

Project manager Frank Castles says to expect the street filled in at an increased rate given there are four contractors currently on the job.

He also says that plants removed from garden beds have been reused across the shire